Artis Montrose

Montrose · Apartment mid-rise

Topped out · July 2026
All developments / Artis Montrose

Project imagery

Artis Montrose — seven-story streetscape rendering

Architectural rendering · Southeastern Company, via Houston Chronicle

What we know

Southeastern Company broke ground in October 2025 on a seven-story, 330-residence apartment complex at the former 'Disco Kroger' site. General contractor Arch-Con confirmed topping out on July 20, 2026; finishing and fit-out remain ahead of an anticipated late-2027 opening. The 528,734-square-foot figure includes residential and structured parking, not purely leasable space.

Explore the complete interactive dossier →

Research sources

  1. General contractor's July 2026 topping-out announcement
  2. General contractor's groundbreaking project record
  3. Southeastern project portfolio